mermaid在markdown中生成gantt图
最近工作中涉及到项目管理的内容。项目管理一般会用到gantt图。笔者不是专职PM,安装Project比较重,不够敏捷,所以尝试寻找轻量级解决方案。不负众望,果然找到标记语言mermaid,并且可无缝集成到typora。mermaid不仅支持gantt图,目前还支持flow chart和sequence chart,很适合展示模块之间的数据流或执行逻辑。
typora对memaid支持的非常好,具体操作参考typora官方文档。代码示例如下
gantt
dateFormat YYYY-MM-DD
title Adding GANTT diagram functionality to mermaid
section A section
Completed task :done, des1, 2014-01-06,2014-01-08
Active task :active, des2, 2014-01-09, 3d
Future task : des3, after des2, 5d
Future task2 : des4, after des3, 5d
section Critical tasks
Completed task in the critical line :crit, done, 2014-01-06,24h
Implement parser and jison :crit, done, after des1, 2d
Create tests for parser :crit, active, 3d
Future task in critical line :crit, 5d
Create tests for renderer :2d
Add to mermaid :1d
section Documentation
Describe gantt syntax :active, a1, after des1, 3d
Add gantt diagram to demo page :after a1 , 20h
Add another diagram to demo page :doc1, after a1 , 48h
section Last section
Describe gantt syntax :after doc1, 3d
Add gantt diagram to demo page : 20h
Add another diagram to demo page : 48h
最开始是描述信息,定义图的类型,日期格式和标题。接下来,每个section就是一个项目。项目中,每一行就是一个任务。任务有名称和属性两部分组成,由英文冒号”:”分开。属性意义:
- done 当前任务已经结束,如果没结束不用标记,必须为第一个。
- crit 当前任务很重要,用红色高亮显示,可用于标记里程碑,必须为第一个。
- 任务id 必须全局唯一,可被后续任务引用,在状态后面(如果有状态描述)。此操作比较灵活,只需修改起始工作的时间,后置(after标记)任务时间全部会改变。如果没有后续依赖,也可省略任务id。
- 最后是任务时间,一般需要两个,开始和结束时间。可以是绝对时间或相对时间,非常灵活。
如果熟悉markdonw,对标记语言有一定了解,5分钟可以学会使用mermaid绘制gantt图管理项目。不过mermaid虽然敏捷,但是其gantt图还是有两个特性没有,
- 无法按百分比显示当前项目进度。
- 没有里程碑标记。
笔者个人理解mermaid是轻量级工具,gantt图的核心功能已实现,上面是非核心功能,可能后续会补足。
以上是使用memmaid绘制gantt图的一些理解,希望对读者的工作有帮助。